Friday 25 February 2011

Limoges Airport's extension project to beging

Construction work on the Aéroport de Limoges extension project is set to begin next week on the 1st March 2011 and is currentley scheduled to finish on the 30th June 2011

The developpoment will include:
  • Repairs and resurfacing of the light aircraft apron
  • Modification to the fueling area
  • Extension of the commercial apron
  • Resurfacing of the Sierra taxiway

During this periode the following temporary mesures will be made:

  • Closure of Sierra taxiway
  • Parking Lima and aéroclub parking will be unusable
  • South commercial apron reduced to 80m x 10m
  • Fueling area will be moved to the Papa parking area

The fueling area will be opened:

  • Monday to Friday : 08h30-09h30 11h00-12h30 18h30-21h00
  • Saturday : 08h30-10h00 18h00-21h00
  • Sunday: 08h00-14h00 18h30-21h00